top of page

PROJECTS

nrw reduction 1.png
incertameter 1.png
z-tech 1 .JPG
Mekkah trainees.JPG
Ranhill 1.jpg
NWC/MIYA Kingston NRW reduction 

I was engaged as a leakage/NRW supervisor and trainer to a total of 20+ leakage technicians, managers, and Engineers. the contract was entering its 3rd year of a 5 yr contract. A certain amount of progress was being made in DMA development. We managed to drop NRW in up to 40 DMA's in a period of 9 months with leaks being 30% to 40% Hidden leaks. lending myself to work with SCA areas Socially Challenged Areas and aiding with the investigation and conclusion of DMA areas finding hidden connections. My work in 2018 helped NWC/Miya to come 4th in the Global Water awards for NRW Savings.

Incertameter, SW4U, Thames Water EU project

Working on a consultancy basis as an active member of SW4EU Smart Water 4 Europe, an NRW Smart metering European funded project. Worldwide Business development, R & D, innovation, Installation, Training, flow and pressure monitoring, Water balance, DMA breakdown, DMA segmenting for localising leakage, Training, P&L responsibilities and Marketing, Logging, Site surveys, Asset management, responsible for the fulfilment of all contractual obligations. Preparation of quotes and bid documents, preparation of health and safety documents and DOMs requirements. Actively aiding the company to attain Achilles Accreditation.

Z-tech, Scottish water, Veolia

I was engaged as a Civils delivery manager due to Z-Tech extending their work portfolio into Scotland. Project managing the installation of 21 bulk meters and bypasses, Sizes of mains work was from small 4” diameter to 54” diameter mains inclusive of bypasses. Having to create safe excavation plans incorporating the use of whalers and trench boxes. Pre-dig surveying, Sitting on high-level DOMS meetings and giving advice on line stops and possible problems to be encountered and how they could be resolved. Managing of work trackers for Veolia aquatrine projects on MOD sites throughout Scotland. Installation of off-grid power. All work completed in scope and on time.

Miahona, NWC Saudi Arabia

Responsible for delivering all NRW projects. Completing Leakage training, monitoring and redesign Project at Albohairat city, Jeddah. Completing within the scope also within time scale. The project consisting of NRW training, water metering, logger deployment, and implementation, pinpointing, Flow monitoring. Responsible for the redesign of a Return loop water system with future expansion incorporated. An immediate upgrade to a variable speed pumping station for fire, Potable and Irrigation water systems.

Completion of Leakage project as above on Chemanol petrochemical plant, Jubail.

Project management and Technical evaluation of industrial wastewater streams in Jubail. Project manager for the analysis, recommendation, and implementation of civil work to overcome the critical deterioration of water network pipework and TSE channel. Installation of new pipework and repair of leaks.  

 

Ranhill Arabia, NWC Saudi Arabia

Based in Saudi Arabia, Riyadh.  Employed as an Isolation\water leakage specialist.  Responsible for the development and effective leakage reduction in Riyadh.  Developing procedures and implementing training of current leakage reduction staff.  To lead isolation teams covering over 150 DMAs to undertake all aspects of water leakage, to provide support to the project manager in reporting and presenting to the client and consultants.  Also providing comprehensive management reports for NRW and operational assistance on the status of department activities.  Directly responsible for training and managing 198 NRW Engineers, technicians and labour of 13 different nationalities.

 

bottom of page